| No |
Nama Pekerjaan |
Bidang |
Diterima |
Selesai |
Nominal |
Keterangan |
Progres |
Diserahkan |
Lihat PDF |
| 01 | Perbaikan CCTV IPAL semanggi (kamera tidak bisa berputar) | Limbah | 04 September 2023 | 04 September 2023 | 4.254.000 | - | - | 06 September 2023 |  |
| 02 | Rewending pompa sumpump bidang limbah IPAL pucang sawit | Limbah | 04 September 2023 | 04 September 2023 | 13.086.000 | - | - | 06 September 2023 |  |
| 03 | Rewending pompa transmisi 90 KW IPA jurug | Produksi | 04 September 2023 | 04 September 2023 | 54.270.000 | - | - | 06 September 2023 |  |
| 04 | Conecting pipa intake no.5 ke pipa header IPA jurug | Produksi | 04 September 2023 | 04 September 2023 | 3.461.000 | - | - | 06 September 2023 |  |
| 05 | Pemindahan trafo intake semanggi | Produksi | 04 September 2023 | 04 September 2023 | 8.052.000 | - | - | 06 September 2023 |  |
| 06 | Pembuatan tangga masuk IPA jebres reservoir utara dan selatan | Produksi | 11 September 2023 | 14 September 2023 | 6.283.000 | - | - | 25 September 2023 |  |
| 07 | Pengangkatan lumpur kolam anaerobik 1 IPLT putri cempo | Limbah | 11 September 2023 | 12 September 2023 | 26.250.000 | - | - | 13 September 2023 |  |
| 08 | Perbaikan elevasi jaringan output reservoir IPA jebres | Produksi | 11 September 2023 | 14 September 2023 | 10.903.000 | - | - | 25 September 2023 |  |
| 09 | Perbaikan pagar keliling bak pasir mata air cokro tulung | Produksi | 11 September 2023 | 12 September 2023 | 37.745.000 | - | - | 13 September 2023 |  |
| 10 | Pengadaan IPAL B3 limbah laboratorium portable | Produksi | 12 September 2023 | 13 September 2023 | 42.654.000 | - | - | 25 September 2023 |  |
| 11 | Pengadaan HPS jasa keamanan, pengemudi, kebersihan dan tenaga bantu | Asset | 12 September 2023 | 13 September 2023 | Terlampir | - | - | 13 September 2023 |  |
| 12 | Pemindahan jaringan perpipaan pembuangan lumpur bak aerasi ke SDB baru IPAL semanggi | Limbah | 14 September 2023 | 19 September 2023 | 35.475.000 | - | - | 25 September 2023 |  |
| 13 | Pembuatan pagar sementara kompleks IPA/IPAL semanggi | Aset | 19 September 2023 | 19 September 2023 | 25.986.000 | - | - | 19 September 2023 |  |
| 14 | Perbaikan pompa submersible aerator no. 1 (3,7 KW) IPAL semanggi | Limbah | 19 September 2023 | 19 September 2023 | 22.881.300 | - | - | 25 September 2023 |  |
| 15 | Perbaikan pompa aerator no. 6 (8,7 KW) IPAL semanggi | Limbah | 19 September 2023 | 19 September 2023 | 55.515.000 | - | - | 25 September 2023 |  |
| 16 | Pengangkatan lumpur bak sedimentasi IPAL semanggi | Limbah | 19 September 2023 | 19 September 2023 | 20.100.000 | - | - | 25 September 2023 |  |
| 17 | Pembuatan TS pengurusan FS uprating IPLT putri cempo | HHK | 20 September 2023 | 20 September 2023 | Terlampir | - | - | 20 September 2023 |  |
| 18 | Pembuatan sistem aerasi sistem blower bak aerasi IPAL semanggi | Limbah | 20 September 2023 | 20 September 2023 | Terlampir | - | - | 20 September 2023 |  |
| 19 | HPS jasa LLTT perwilayah kecamatan TA 2024 | Limbah | 20 September 2023 | 20 September 2023 | Terlampir | - | - | 20 September 2023 |  |